Tynte Tower (North)

  • Concrete slabs are now poured to level 9.
  • Jump form (lift) core is poured to level 12.
  • Fitout works of the apartments are ongoing and the façade works are underway on level 3.



Centenary Tower (Central)

  • Concrete slabs are now poured to level 10.
  • Jump form (lift) core is poured to level 12.
  • Fitout works of the apartments are ongoing, while the façade works are underway on level 4 and stud walls are standing on level 3.



Archer Tower (South)

  • Concrete slabs are now poured to level 8.
  • Jump form (lift) core is poured to level 12.
  • Fitout works have commenced setout to the apartments at level 3.